Scoping project approach in the developing world
Contents |
[edit] The challenge
Misalignment of design cultures handicaps infrastructure in the developing world.
Many developing countries lack a clear engineering and construction culture. These countries receive loans and grants from donor countries and multi-lateral development banks. Yet, the consistent pipeline of funds is not enough to nurture need for a local engineering and construction (E&C) culture.
Such a culture would guide elements such as the level of design expected by construction contractors and the inclusion of regional/local characteristics and constraints.
As a result, owners receive insufficient feasibility and design work. Public utilities especially expect design professionals to produced documents appropriate for the market. However, the design staff is rarely local.
Most work in developed countries and have never been to site or worked in the developing context. They do not understand the local or regional market and sometimes such a market doesn’t exist. They defer to processes, habits and characteristics of the developed environments they know best. This leads to specifications not suited for the location, drawings that assume too much from the contractors and Invitations for Bids that the market cannot respond to substantively.
The ultimate outcome is a mismatch of E&C philosophies between the contracted parties. This often requires more design, delayed works, delayed site access, confusion and additional cost and time to the owner and/or lender.
Given the many challenges faced by the developing world to successfully accomplish infrastructure projects, it would benefit owners and designers to address fundamental questions early in scoping and feasibility. These most basic questions (e.g. defining the amount of design sufficient for the market) are not asked but assumed.
A manual can guide designers to better understand their clients’ most elementary conditions. Such an application can ensure not only a more effective construction phase (match the right contractors to the right work) but also consider characteristics to operations, maintenance and ultimately decommissioning.
[edit] The idea
A concise manual of questions to address common misunderstandings
The approach to address the challenge is a concise process manual. The document’s purpose is to guide the owner to understand their requirements when seeking design services and guide a scoping and/or feasibility phase meeting with the designer. It will help participants uncover ambiguity in bias and better define information required to bring a project through the phases of design, construction, operations and maintenance.
A model to this manual already exists in the United Kingdom’s Green Book. The Green Book, focused on Public-Private Partnerships, asks a series of investigative questions into order to assess the validity and readiness of a PPP arrangement. It highlights areas for improvement before investment action is committed.
Like the Green Book, the manual’s components will be investigative criteria as well as definitions on common ambiguity. For example, the term 'bid ready design' has different meanings across the world.
In North America, that means a level of design not requiring further design by the Contractor.
In the European tradition this can mean significant design by the contractor for a traditional construction project.
In the South African tradition the bid level requires significant just in time designs from the designer during construction.
Now imagine an international development project with professionals from all these traditions. It is an ample environment for confusion, chaos and blame. The benefit of the manual will be to focus attention on these differences early so that professionals can act with clear understanding and intention of one another.
[edit] The impact
If successful, there can be significantly less confusion, delay and additional cost during the construction period.
Normally, contractors price in risk to their bid; however, in the technically acceptable lowest bid often used in the developing world, it is less advantageous to the bidder if they want to win. It is common for works to grind to a halt while contractors wait for additional design, access to site and/or resettlement of project affected people. This new design and idle time provides opportunity for claims and compensation. As a result the projects lose focus and relationships between parties become adversarial.
This manual will direct the owner and design professionals to address the common pitfalls of work in the development context. The project team will better know the type and level of design required for the market actors available. They will be able to choose an appropriate project delivery approach for the asset and engage earlier in a discussion with the market during scoping and feasibility.
[edit] The barriers to innovation – and the solutions
This will not be a new process, but elaboration of an existing process.
Three barriers must be overcome for implementation; that is perceptions of project validity, additional time and additional bureaucracy. First is the perception that this issue is not real or easily overcome in project elaboration. However, the Millennium Challenge Corporation, the World Bank and many owners and developers have experienced delays and costs increases as a result of poor alignment with the market. A logical argument using expert and implementation experiences can successfully lay out the call for action.
The second barrier and third barriers are closely related. That is additional evaluation is more work and delays implementation. Everyone has experienced more bureaucracy as a result of errors made. This approach leads to onerous and ad-hoc actions to mitigate a reoccurrence and often not effectively.
This effort instead comprehensively addresses many integrated challenges while not adding another process. This is better definition to the existing processes of scoping and feasibility. The time and budget spent in front end planning will return greater savings in implementation.
[edit] The way forward
Develop, Pilot and Iterate
This paper represents the earliest conception of the idea. The most effective way forward is first a donor to fund the development of a draft manual with iterative input from other donor life cycles. The lead developer should be in a position to pilot the use of the manual and incorporate those lessons into the first edition.
Written by Mark Tkach, Director Infrastructure, Millennium Challenge Corporation (MCC), USA.
This article was originally published on the Future of Construction Knowledge Sharing Platform and the WEF Agenda Blog
[edit] Find out more
[edit] Related articles on Designing Buildings Wiki
- A better investment framework for Africa.
- Flexibility in PPP Contracts: Best practices from countries where Abertis operates.
- Managing the procurement process.
- Project controls in a post-BIM world.
- Public private partnerships PPP.
- These giant infrastructure projects are set to reshape Africa.
- Unprecedented innovation and new technologies on the horizon.
Featured articles and news
CIOB launches global mental health survey
To address the silent mental health crisis in construction.
New categories in sustainability, health and safety, and emerging talent.
Key takeaways from the BSRIA Briefing 2024
Not just waiting for Net Zero, but driving it.
The ISO answer to what is a digital twin
Talking about digital twins in a more consistent manner.
Top tips and risks to look out for.
New Code of Practice for fire and escape door hardware
Published by GAI and DHF.
Retrofit of Buildings, a CIOB Technical Publication
Pertinent technical issues, retrofit measures and the roles involved.
New alliance will tackle skills shortage in greater Manchester
The pioneering Electrotechnical Training and Careers Alliance.
Drone data at the edge: three steps to better AI insights
Offering greater accuracy and quicker access to insights.
From fit-out to higher-risk buildings.
Heritage conservation in Calgary
The triple bottom line.
College of West Anglia apprentice wins SkillELECTRIC gold.
Scottish government launch delivery plan
To strengthen planning and tackle the housing emergency.
How people react in ways which tend to restore their comfort.
Comfort is a crucial missing piece of the puzzle.
ECA launches Recharging Electrical Skills Charter in Wales
Best solutions for the industry and electrical skills in Wales.
New homebuilding skills hub launch and industry response
Working with CITB and NHBC to launch fast track training.